News
Second phase of Mildred Hailey redevelopment underway
Seven-story Centre Street building to be razed

Three months after the ribbon cutting and over three years since the groundbreaking for Mildred Hailey Phase one at 4+6 Lamartine Street in Jamaica Plain, the second phase of the mixed-income redevelopment experiment of the 6.9 acres is getting started.
As planned in February of 2017, demolition for the second of the sub-phases of the seven buildings would not begin until the first was occupied.
This Building Two and Building Three will be more dramatic in large part because it will require the demolition of the seven-story 265-267 Centre St. structure opposite the Lamartine traffic light.
That building – together with the low-rise, three-story 52-54 Lamartine Street at the Southwest Corridor Park (SWC) – are empty and fenced off.
Building Two and Three are ventures of JPNDC and Urban Edge; they filed a joint notification form on Nov 4, 2022.
Building Two (52 Lamartine and 267 Centre St.) will be built, owned and managed by the Jamaica Plain Neighborhood Development Corporation (JPNDC). Building Three (960-984 Parker St., now totally gutted) will be built, owned and managed by Urban Edge.
Building Two will be a six-story, 65-unit apartment building designed by Prellwitz Chillinski Architects (PCA) as a “gateway building” adjacent to the Jackson Square T station.
The Boston Planning and Development Agency (BPDA) board approved Building Two in December 2023. Twenty-three apartments, nine of which are three-bedroom units, will be for returning Boston Housing Authority (BHA) tenants.
BHA administrator and former city councilor Kenzie Bok spoke at the Nov. 8, 2023 BPDA meeting for Buildings Two and Three.
“Our core commitment is the absolute right to return one-to-one replacement,” she said. “We’re very proud of this multi-income development.”
“I want to emphasize what an important priority this plan is to us.”
Eight of the apartments in Building Two will be new project-based vouchers (at or below 50 percent area median income [AMI]) and 34 will be leased at 60 percent AMI.
In Nov 2023 Marc Eclipse of PCA – who also designed 4+6 Lamartine – described the long, 12-bay apartment house, largely faced in red brick panels, that lines up with 6 Lamartine.
A long building, it parallels the SWC Park and the T station. It is characterized by a low oblong first floor podium for the community room that faces Centre Street and retail space.
Eclipse said at the Nov. 2023 BPDA meeting “there is considerable open space with a wide set back to line the building up with the Jackson Square station.”
The major change was that the Boston Transportation Department (BTD) did not want Lamartine Street extended to Centre Street, as originally planned, apparently to avoid another intersection; there are already three, but also to avoid a shortcut from Heath Street,
Instead landscape architect Shauna Gillis Smith has designed a low shaded plaza as a public space and a pedestrian connection to 4-6 Lamartine.
Smith said at the Nov. 2023 meeting she planned a “considerably shady open space but the plantings would be kept low so nobody can hide behind them”
According to the JPNDC demolition is “anticipated to take place in January 2027.”
In 2021 the BPDA estimated the cost of Building Two at $38 million; the estimated cost now, according to the JPNDC, is “approximately $43 million.”
When completed, Building Two will be managed by Peabody Properties in cooperation with the BHA, which will manage the vouchers.
Building Three, designed by Andres Bernel of Jonathan Garland Architects (JGA), will be six stories with 60 apartments.
It faces three streets: Parker, Bickford and Lamartine, and is directly opposite 6 Lamartine.
The 960-964 Parker building is gutted and interior abatement is completed according go the BHA. “Full demolition is expected to begin sometime in December.”
Demolition will be done ahead of the JPNDC buildings; demolition for Building Two will take longer “simply due to the size of the buildings” according to the BHA.
Bernel from JGA has designed Building Three with undulating walls and two main entrances to fit the site that faces 4-6 Lamartine.
Bickford Street will be the main façade and the most important, with undulating walls according to Garland at the Jan. 12, 2023 BPDA meeting.
Six stories will be faced with fiber cement panels and the first floor faced with brick.
As with every other new building built or under construction in the redevelopment of Mildred Hailey, there is a strict one-to-one replacement policy that the BHA has repeated at every public meeting since 2017. At Building Three, 22 apartments will be reserved for returning tenants, seven at two bedroom and eight at three bedrooms.
In addition there will be eight project-based vouchers added at 30 percent AMI; four will be one bedroom.
The remaining 30 units will be subsidized with tax credits at 60 percent AMI.
Judy Cohen has been the relocation consultant since 2022 and as she explained at the Jan. 12, 2023 BPDA meeting, relocations for Buildings Two and Three will take place when 4-6 Lamartine are complete.
According to the BHA in a recent message to The Bulletin, “There are 91 replacement units at 4-6 Lamartine Street, and the majority have gone to households at Mildred Hailey.”
According to Urban Edge, the total cost for Building Three “is projected to be $62 million.”
The BHA told The Bulletin in a recent message that although the redevelopment of Mildred Hailey has so far taken five years and will take longer to complete the other phases (estimated to be in 2031) “the BHA is the long term steward of Mildred Hailey.”
“The BHA administers the Section 8 vouchers and our staff are active in maintaining and servicing the buildings slated for disposition before they are in new ownership.”
“We maintain the broader campus of Mildred Hailey.”